ABC Construction had some general labor that were used on projects. The hourly wage for these workers was $11/Hr. Following is the information available:
10 workers worked for 8 hours on Monday.
Wednesday through Friday they worked for 10 hours.
On Saturday they worked for 7 Hours.
Another group of 4 employees worked for 8 hours a day for 4 days.
ABC Construction wants to add a 12% increase to the profits to offset the overtime payments. Based upon the above information only, what is the hourly rate that ABC construction should charge the customer?